Golden Pass LNG
Industrial | Refining/Petrochemicals
Industrial
Refining/Petrochemicals
Project Overview
Baker’s contract on the project consisted of total package concrete including 5 complete LNG containment tanks, slabs, walls and concrete roofs. Baker poured in 10 day cycles, requiring major coordination between the moving parts and people. Each pour was required to go through pre-pour and post-pour inspections to ensure quality and safety. Additionally, each part of the structure was broken down into Individual Transition Plans (ITP) which included a breakdown of how each step of the process was addressed. Upon completion, Baker successfully poured over 120,000 cubic yards of concrete.
Client
Golden Pass LNG, a joint venture between Qatar Petroleum, ExxonMobil and ConocoPhillips
Location
Sabine Pass, TX
Size
120,000 cy
Completion
June 2009