Project Overview

Baker Concrete was contracted by Garney-Wharton Joint Venture for this Design Build project. The scope of work for this project consisted of six separate structures for a total of 28,036 CY, 2,772 tons of reinforcing steel, and over 20,000 linear feet of pvc waterstop. The project began in October of 2017 and was substantially complete in July of 2018 for a duration of 9 months. This Project Recieved an ABC Eagle Award. This project was completed by our Tampa, Florida, team.

Client

Garney-Wharton JV

Location

Tampa, FL

Size

28,036 CY

Completion

July 2018