Adams County Prototype
Industrial | Clean Power
Industrial
Clean Power
Project Overview
Baker was contracted by Siemens Wind Power to aide in the development and construction of a segmental precast concrete wind tower. The Adams County (Iowa) Prototype became the highest wind turbine in the United States when completed in January 2016. The hub height is 115 meters (377 feet).
Client
Siemens Wind Power
Location
Corning, IA
Size
1,200 cy
Completion
January 2016